Citation
Abstract
The previous article in this series described the results of the radio-frequency Compatibility Test Program for Viking test models of the Orbiter and Lander conducted at the Compatibility Test Area in August and September 1974. This article covers the initial phases of the network implementation for the Viking Project with particular emphasis on significant organizational changes that were found necessary to bridge a hitherto unforeseen gap between the higher level subsystem schedules and the lower level engineering modification schedules.
Details
- Volume
- 42-25
- Published
- February 15, 1975
- Pages
- 37–42
- File Size
- 436.3 KB