Abstract
Progress of installation and test of the DSS 43 and DSS 63 high-power transmitters is traced through procurement, installation, and test of the equipment at DSS 13 to overseas shipment and installation status at DSS 63 as of January 25, 1975. The schedule for this activity is to have the DSS 63 subsystem installed, tested, and transferred to operations for the Viking project by mid-July 1975, and the DSS 43 subsystem operational by mid-October 1975.