The Southern California Edison Company issued a new time-of-day rate schedule for the Goldstone Complex which substantially increased the cost of commercial power during the daily high usage periods. Subsequently, a Power Load Management Plan was developed which would utilize the unique power generating capabilities of the stations to reduce the stress on the Edison Company’s reserve capacity and reduce the cost of electrical power at the stations. The plan, which has now been implemented, has greatly reduced the cost of Goldstone electrical power by completely eliminating the use of commercial power during the Edison Company’s high usage periods each day.