Because of the February budget constraints, previous plans and schedules for Viking have been reworked to minimize the impact on readiness dates committed to the Viking Project. An improved implementation schedule has been developed to manage hardware and software progress toward Viking configurations in the DSN. Several significant reviews have been held and some new problem areas identified. In the particular case of DSS longitude accuracy, a task team has been formed to try to resolve the problem by September of this year. Operations activity in support of Viking is also introduced in this issue.